Regency Pipeline: Project Update

Regency Energy Partners is hard at work on expanding its pipeline network to serve the Haynesville Shale. The Haynesville expansion is a joint venture with GE Energy Financial Services. The project is broken into three segments, and the company has broken ground on the first leg (Bienville) already. Here is a quick summary:

- 36" Bienville Line: Permits and right-of-way acquired, construction has begun
- 36" Elm Grove Line: Permits and right-of-way acquired, surveyed, no construction yet
- 42" Winnsboro Line: Permits acquired, 99% of right-of-way acquired, final FERC application upcoming, permits for two compression stations received

Regency expects to have the pipeline complete and in service by the end of 2009.